India BESS Tenders 25–31 October 2026: SECI's 16 GWh Rajasthan–Gujarat Auction Leads the Pipeline

Writer: Shilpan Shukla
Shilpan Shukla
Nov 4
7 min read

Seven new battery energy storage opportunities opened for bidding or surfaced on procurement portals this week, and two notable award milestones were reported. The headline is the Solar Energy Corporation of India's (SECI) new Request for Selection for 4,000 MW/16,000 MWh of standalone BESS across Rajasthan and Gujarat, one of the largest storage auctions India has yet floated. Around it sit a Ladakh solar-plus-storage programme, a 1,200 MW solar EPC package with land reserved for storage, a utility tender for mobile truck-mounted battery units, and a handful of consultancy and distributed-storage bids that show how widely storage is now being written into public procurement. On the results side, Coal India's 750 MWh Telangana project has a lowest bidder, and Gujarat's regulator has formally adopted tariffs for 450 MW/900 MWh of two-hour storage. Details, dates and links follow.

New Tenders This Week

SECI Standalone BESS RfS, 4,000 MW/16,000 MWh – Solar Energy Corporation of India (SECI)

SECI issued the RfS on 28 October to select developers on a build-own-operate basis under tariff-based competitive bidding, split into Package I: 2.5 GW/10 GWh in Rajasthan (projects from 50 MW/200 MWh up to 625 MW/2,500 MWh) and Package II: 1.5 GW/6 GWh in Gujarat (50 MW/200 MWh minimum, 375 MW/1,500 MWh cap per bidder). Systems are designed for four hours of charge and four hours of discharge per daily cycle, with at least 51% of charging energy from renewable sources and central financial assistance of ₹15 lakh/MWh, about ₹2,400 crore across the 16 GWh. Online bids close on 19 November 2026, with the RfS timeline running to 23 November. Saur Energy · Mercom India · Tenderkart

1,000 MW Solar with 1,000 MW/4,000 MWh Storage at Pang, Leh – SECI

SECI notified on 21 October a two-route programme for Pang in Ladakh's Leh district: an EPC tender for a 1,000 MW (AC) solar plant with a 1,000 MW/4,000 MWh BESS, and a developer-mode RfS for 1,000 MW of ISTS-connected solar with the same storage. A bidder site visit took place on 27 October under Ladakh hill council permits; bid deadlines, eligibility terms and PPA tenure will follow with the formal documents. The 4,000 MWh equals one-third of the 12 GWh BESS planned for Ladakh's 13 GW renewable hub. Vyqon

1,200 MW ISTS Solar EPC with Storage-Ready Land, Anantapur – NTPC Renewable Energy Limited (NTPC REL)

NTPC REL released its Invitation for Bids on 29 October for up to 1,200 MW of solar near its existing Anantapur project in Andhra Pradesh, split into a 900 MW Block-I and a 300 MW Block-II. The EPC scope includes land acquisition, which must cover the area required for a proposed BESS, plus evacuation works and three years of O&M; the notice reserves space for storage rather than fixing a battery rating. Bid security is ₹50 crore, ₹20 crore or ₹100 crore depending on the block; pre-bid is on 13 November and bids are due 27 November. SolarQuarter

Truck/Trolley-Mounted Mobile BESS Supply – Tata Power Company Limited

Tata Power floated a multi-state tender on 27 October for the supply of truck- or trolley-mounted mobile battery energy storage systems, an increasingly popular format for network support, outage cover and temporary peak management. Submission is offline, with an EMD of ₹2.5 lakh and a ₹2,000 document fee; bids are due 2 November 2026, and unit ratings are set out in the tender document. This is one of the few packaged, factory-built BESS purchases in the week's list. TenderDetail

DPR Consultancy for 650 MW Hybrid Renewable Project with 600 MWh BESS, Zara, Kachchh – Gujarat Power Corporation Limited (GPCL)

GPCL invited bids on 30 October for a consultant to prepare the detailed project report for a 650 MW (AC) hybrid renewable energy project paired with 600 MWh of battery storage at Zara in Kachchh district, Gujarat. The estimated value is about ₹51 lakh and bids are due 4 December 2026. A DPR tender is an early signal: the EPC or developer procurement for the project itself is likely to follow in 2027. Tenderkart

Grid-Connected Rooftop Solar Hybrid with Battery Storage – Lakhimpur Kheri District Cooperative Bank, Uttar Pradesh

Posted on GeM on 28 October, this bid covers design, supply, installation, commissioning and maintenance of a grid-connected rooftop solar plant in hybrid configuration with battery storage for the district cooperative bank in Kheri, Uttar Pradesh. The estimated value is about ₹1.5 crore, and bids are due 7 November 2026. It is small, but it reflects the growing number of commercial and institutional buyers asking for batteries behind the meter. Tenderkart

100 MW Floating Solar with 100 MW/400 MWh BESS, Lower Wardha – Maharashtra State Power Generation Company (MAHAGENCO)

MAHAGENCO's notice inviting tender, dated 19 October, covers design, engineering, supply, erection, testing and commissioning of a 100 MWac floating solar plant with a four-hour 100 MW/400 MWh BESS, a 33/132 kV pooling substation and the transmission link, followed by maintenance of the floating plant. The project is located at the Lower Wardha reservoir in Maharashtra. Online bids are due 13 November 2026. Tenderkart

Tender Winners

Coal India's 187.5 MW/750 MWh Choutuppal BESS EPC – Pace Digitek Emerges as Lowest Bidder

Pace Digitek Limited was reported on 27 October as the L1 bidder at ₹1,073.74 crore for the engineering, procurement and construction of Coal India Limited's 187.5 MW/750 MWh battery energy storage system at Choutuppal, Telangana, including 15 years of comprehensive O&M. The price works out to roughly ₹1.43 crore per MWh on a full-lifecycle basis and was reportedly the lowest among eleven bidders. Award formalities with Coal India are the next step. Tenderkart on LinkedIn

GUVNL Phase IX, 450 MW/900 MWh – Gujarat Regulator Adopts Tariffs for NLC India Renewables and Sun Drops Energia

On 29 October the Gujarat Electricity Regulatory Commission approved the tariffs discovered in GUVNL's Phase IX standalone storage auction. NLC India Renewables won 275 MW/550 MWh at ₹2,31,989 per MW per month and Sun Drops Energia, part of KP Group, won 175 MW/350 MWh at ₹2,31,990 per MW per month. The two-hour projects carry 95% annual availability and 85% monthly AC-to-AC efficiency obligations, with GUVNL supplying charging power. Mercom India · GreentechLead

Reading the Week: Four Signals for the BESS Value Chain

1. Procurement is moving from gigawatt-hours to tens of gigawatt-hours. SECI's previous standalone round this month covered 800 MW/3,200 MWh. This week's RfS is five times larger by energy, with a full 6 GWh package in Gujarat. With central assistance of ₹15 lakh per MWh built into the structure, the programme is designed to keep tariffs competitive: the Gujarat results adopted this week, at roughly ₹2.32 lakh per MW per month for two-hour storage, sit very close to the ₹2.38–₹2.40 lakh range discovered by Maharashtra's distribution utility in September. Four-hour products such as SECI's will price differently, so comparisons should always be made on a duration-adjusted basis.

2. The conversation has shifted from tendering to delivery. At Energy Storage Summit India this week, a CEA official put operational BESS at 5.3 GWh against roughly 185 GWh under development. SECI's power systems director told the same event that developer participation in its tenders has grown from six or seven established names to more than twenty, but that construction typically takes 15 to 18 months and that financial closure and land availability are being monitored closely. Rating agency commentary cited this week expects 45–50 GWh to be commissioned across FY2027 and FY2028, with 8–9 GWh of awarded capacity facing elevated delay risk. For equipment suppliers, that translates into pressure on lead times, quality documentation and commissioning support, not just price.

3. Packaged, factory-built systems are getting their own tenders. Tata Power's mobile BESS purchase and the cooperative bank's hybrid rooftop bid are small beside a 16 GWh auction, but they point to a steady stream of container-, trolley- and cabinet-scale demand from utilities, institutions and commercial users. The same ESS India panel noted that Delhi's BSES is planning storage at more than 910 constrained distribution locations. Buyers of that kind want proven, standardised, locally serviceable units, and they tend to procure through short, document-heavy tenders where bid security and technical qualification matter as much as unit price.

4. Domestic content is becoming a design variable. SECI's director acknowledged this week that India still relies on imported cells, while domestic participation has deepened in packs, racks, container systems, power management and controls. That is exactly the layer where local assembly adds value: integration, thermal and fire-safety design, protection, controls and after-sales service. Tamil Nadu's decision this week to mandate battery storage for new solar and hybrid projects, and Rajasthan's plan to pilot India's first 250 kW sodium-ion storage system in Jaipur, widen that integration opportunity further across chemistries and project types.

Live Opportunities Worth Tracking

A few open procurements deserve a place on any bid calendar. Madhya Pradesh Power Management Company's Request for Selection for 282.5 MW/1,130 MWh of VGF-supported BESS on a BOO basis, first issued in May, has now reached its ninth corrigendum and closes on 17 November, with technical bids opening on 20 November. Rajasthan Rajya Vidyut Utpadan Nigam is running two large standalone tenders under tariff-based global competitive bidding: 1,500 MW/6,000 MWh (estimated at ₹9,600 crore, bids due 12 January 2027) and 250 MW/1,000 MWh (estimated at ₹1,600 crore, bids due 5 January 2027). REMC Limited's selection of developers for 17 MW of solar with 12.5 MW/50 MWh of BESS on vacant railway land at Dahod, Gujarat, remains open until 16 November. Dahod is within easy reach of Ahmedabad-based suppliers, and railway-land projects are typically bid by developers that need a local integration partner.

What to Do With This Week's Information

Bidders on the SECI RfS should start now on connection, land and charging-power arrangements, since the 51% renewable charging requirement and the four-hour discharge window shape both system sizing and revenue. Suppliers should align battery, PCS and container specifications with the performance parameters in the RfS, including availability and round-trip efficiency obligations, and prepare factory test records and safety documentation early. Smaller procurements such as mobile and rooftop-hybrid BESS reward readiness: current type-test reports, BIS and IEC compliance, service coverage and clear warranty terms.

Recent Posts

See All
India BESS Tenders This Week: 7–14 November 2026

Battery storage procurement in India kept its momentum in the week of 7–14 November 2026, with eight new tender notices covering utility-scale packages, floating solar-plus-storage, transmission works

 
 
 
India BESS Tenders Weekly Brief - 10-17th October

India's battery storage procurement pipeline kept its momentum this week, with eight new tenders and notices entering the market and three significant awards announced. The headline items are MAHAGENC

 
 
 