India BESS Tenders Weekly Brief: 18–24 October 2026

Writer: Shilpan Shukla
Shilpan Shukla
Oct 26
6 min read

By Shilpan Shukla, Founder, Urjapod Energy · Ahmedabad · 24 October 2026


India's battery storage procurement engine kept running at full speed this week. Five fresh opportunities reached the market between 13 and 24 October 2026, led by Haryana's solar-plus-storage request for selection (issued 22 October), Telangana's 2,000 MW firm-and-dispatchable round-the-clock (FDRE-RTC) tender backed by 2,000 MWh of storage, and a short-term storage-capacity procurement from Andhra Pradesh's APCPDCL, alongside an overseas floating solar-plus-BESS EPC from NTPC and the live Gujarat Phase-X standalone BESS tender. On the results side, ACME Solar signed a 300 MW/1,200 MWh assured-peak-power PPA with SECI, and Bondada Engineering secured a 20 MW/120 MWh vanadium redox flow battery project from GIPCL. Regulators also moved: the Central Transmission Utility set a four-hour minimum for certain BESS connectivity applications, Gujarat notified its battery storage regulations, and Kerala published a storage-friendly tariff framework. Below is everything developers, EPC firms, integrators and assemblers need to know.

New Tenders This Week

Haryana Power Purchase Centre: Solar-Plus-BESS Projects (Haryana)

The Haryana Power Purchase Centre, the joint procurement forum of Uttar Haryana Bijli Vitran Nigam (UHBVN) and Dakshin Haryana Bijli Vitran Nigam (DHBVN), invited bids on 22 October 2026 to develop ground-mounted solar power projects integrated with battery energy storage systems within the state. Bids are due on 17 November 2026, and the solar capacity, storage ratings and site schedule are set out in the bid documents on the issuers' portals. The tender is a notable signal that northern discoms are moving from standalone storage to bundled solar-plus-storage supply to manage evening peaks. Mercom India

TGGENCO: 2,000 MW FDRE-RTC Tender with Storage Component (Telangana)

Telangana's generation utility has floated a 2,000 MW FDRE-RTC tender to supply Telangana's distribution companies, with bids due 4 November 2026. Developers may bid between 50 MW and 1,000 MW of cumulative contracted capacity, and projects can be sited anywhere in India, although Telangana STU-connected projects must be installed in Telangana. The buyer can call six peak hours a day with day-ahead notice, with minimum delivery of 90% in peak hours, 50–60% in solar hours and 70% in other non-solar hours, measured in 15-minute blocks. The companion Telangana procurement includes 2,000 MWh of FDRE battery storage, and batteries must be co-located with the renewable generation. The tender document costs about ₹50,000 including GST. Saur Energy | Biginfo

APCPDCL: Four-Hour Storage Capacity from Commissioned BESS (Andhra Pradesh)

The Andhra Pradesh Central Power Distribution Corporation (APCPDCL) sought bids on 13 October 2026 to procure four-hour energy storage capacity from fully commissioned battery energy storage systems, under a two-year contract. This is a different model from the build-own-operate auctions that dominate the market: the buyer contracts capacity from assets that already exist, which creates a revenue route for operating merchant and captive batteries. The bid window closed on 14 October 2026, so the outcome is worth watching as a pricing benchmark for operating assets. Mercom India

GUVNL: 1,000 MW/4,000 MWh Standalone BESS, Phase-X (Gujarat)

Gujarat Urja Vikas Nigam (GUVNL) issued its Phase-X tender in August 2026 for 1,000 MW of standalone battery storage with 4,000 MWh of energy capacity, four-hour duration. Projects can be located anywhere in Gujarat and connected to the intra-state transmission system under a build-own-operate model, with developers signing battery energy storage purchase agreements with GUVNL. Selection is by e-bidding followed by an e-reverse auction. The minimum bid is 65 MW/260 MWh, systems may cycle up to twice daily (capped at 480 cycles per contract year), and minimum annual availability is 95%. Online bids closed on 14 September 2026, and the auction outcome is the next milestone to track. Mercom India | pv magazine India

NTPC: EPC for Floating Solar and BESS at Tamarind Falls Reservoir (Mauritius)

NTPC has invited EPC bids for a 15 MW floating solar and 60 MWh battery storage project at the Tamarind Falls Reservoir in Mauritius, with bids due on 7 December 2026. Though the site is overseas, the tender matters to Indian suppliers: it shows a major Indian PSU exporting its floating-solar-plus-storage template, and it opens a potential export channel for Indian-assembled battery systems, containers and balance-of-plant. MVA Pulse | SolarQuarter

Tender Winners

ACME Solar Signs 300 MW/1,200 MWh FDRE-IX PPA with SECI

ACME Solar, through its subsidiary ACME Greentech Twenty Pvt Ltd, signed a power purchase agreement with the Solar Energy Corporation of India for 300 MW/1,200 MWh of assured peak power from ISTS-connected renewable projects under SECI's FDRE-IX tranche. The tariff is ₹6 per kWh. ACME will supply 4 MWh per MW of contracted capacity during any four non-solar hours each day, with minimum monthly availability of 90%, using a solar-plus-BESS mix and night-time grid connectivity it already holds. The company reports 4,310 MW of under-construction capacity with signed PPAs and 4.96 GWh of BESS in its portfolio. pv magazine India | MVA Pulse

Bondada Engineering Wins 20 MW/120 MWh Flow Battery Project from GIPCL (Vadodara)

Bondada Engineering received a letter of intent from Gujarat Industries Power Company Ltd (GIPCL) for a 20 MW/120 MWh vanadium redox flow battery system at GIPCL's 165 MW gas power plant complex in Vadodara, Gujarat. The scope covers engineering, procurement and construction plus 10 years of operations and maintenance, with completion targeted within 18 months of the notice of award. Bondada positions it as India's largest grid-scale vanadium flow battery system, following its 100 MWh VRFB project for NTPC Renewable Energy at Khavda. It is a rare long-duration, non-lithium award in a market dominated by lithium iron phosphate. pv magazine India

Policy and Regulatory Moves That Shape the Next Tenders

Three regulatory developments landed on 22 October and will shape how upcoming tenders are written.

CTUIL's four-hour rule. The Central Transmission Utility of India set a minimum discharge duration of four hours for specific BESS grid-connectivity applications, while eligible applications under the right-of-first-refusal category need only two hours. The minimum varies by connectivity category and General Network Access provisions. For developers, this effectively standardises four-hour systems as the default for connectivity-linked storage, which is consistent with the four-hour designs in SECI, GUVNL, MAHAGENCO and APPCC tenders. Mercom India

Gujarat's battery storage regulations. Gujarat's electricity regulator notified its grid-interactive battery energy storage regulations, giving the state's utilities and developers a rulebook for connection, operation and dispatch. Given that GUVNL is India's most prolific storage buyer, clear regulation reduces execution risk for winners of its Phase-X and later auctions.

Kerala's tariff framework. Kerala published a tariff framework with specific provisions for battery and pumped storage, an early sign that southern states are building regulatory scaffolding to host standalone storage.

What This Week Tells Us About the Market

Bundled products are overtaking standalone batteries. Of this week's fresh opportunities, the Haryana and Telangana tenders both pair generation with storage. FDRE-RTC and solar-plus-storage structures reward developers who can guarantee delivery windows rather than simply provide megawatt-hours, and ACME's ₹6/kWh assured-peak-power price is a useful reference point for what four hours of firm evening supply is worth.

Discoms are experimenting with contract structures. APCPDCL's two-year capacity procurement from commissioned batteries is a different instrument from a 12-year build-own-operate agreement. If it succeeds, expect more distribution utilities to contract existing assets for peak support, a lower-capex path to storage that also helps early movers recover investment faster.

Gujarat remains the pace-setter. Phase-X follows earlier GUVNL rounds with the same disciplines: on-demand dispatch, up to two cycles per day, a 480-cycle annual cap and 95% availability. These parameters are becoming de facto industry norms that bidders should design to, from cell selection to thermal management and battery management system (BMS) warranties.

Long-duration alternatives are earning contracts. Bondada's vanadium flow award shows that a niche for non-lithium chemistries exists where utilities value cycle life and safety at gas-plant and thermal-plant sites.

Export potential is emerging. NTPC's Mauritius EPC is a reminder that Indian PSUs are carrying domestic engineering practices overseas, and that Indian supply chains can follow.

What Developers, EPCs and Assemblers Should Do Next

For bidders, the practical takeaways this week are straightforward. Telangana's 4 November deadline and Haryana's 17 November deadline leave limited time to line up land, grid connectivity and storage supply, so tie-ups with cell and pack suppliers should be locked in now. Bid documents in these tenders increasingly emphasise delivery performance measured in 15-minute blocks, which puts a premium on accurate round-trip efficiency data, rated cycle life and reliable BMS and energy management software.

For the manufacturing and assembly ecosystem, the demand picture is encouraging. Every tender above implies containerised enclosures, power conversion systems, thermal management and controls that can be integrated locally. As domestic content requirements tighten across viability-gap-funded programmes, assemblers that can certify cell provenance, test against Indian grid codes and provide dependable after-sales support will be better placed to partner with winners. At Urjapod Energy, our focus in Ahmedabad is precisely this layer: engineering and assembling battery energy storage systems for Indian conditions, from commercial and industrial installations to utility-scale blocks.

Dates to Watch

  • 4 November 2026: Telangana FDRE-RTC bid submission deadline.

  • 17 November 2026: Haryana Power Purchase Centre solar-plus-storage bid deadline.

  • 7 December 2026: NTPC Mauritius floating solar-plus-BESS EPC bid deadline.

  • Pending: Outcome of GUVNL's Phase-X reverse auction and the APCPDCL capacity procurement.

India's storage pipeline shows no sign of slowing. With four-hour duration becoming standard, bundled supply formats multiplying and regulators filling in the rulebook, the next few months should bring a steady flow of awards and fresh tenders. We will continue tracking each one in this weekly brief.

Tender details are drawn from published trade-press reports and issuer announcements. Bidders should verify capacity, eligibility and deadlines against the official tender documents before submitting bids.

Recent Posts

See All
India BESS Tenders This Week: 7–14 November 2026

Battery storage procurement in India kept its momentum in the week of 7–14 November 2026, with eight new tender notices covering utility-scale packages, floating solar-plus-storage, transmission works

 
 
 
India BESS Tenders Weekly Brief - 10-17th October

India's battery storage procurement pipeline kept its momentum this week, with eight new tenders and notices entering the market and three significant awards announced. The headline items are MAHAGENC

 
 
 